Given below is an excerpt from a management performance report:
budget actual difference
contribution margin $1,000,000 $1,050,000 $50,000
controllable fixed costs $ 500,000 $ 450,000 $50,000
the manager's overall performance
a. is 20% below expectations.
b. is 20% above expectations.
c. is equal to expectations.
d. cannot be determined from information given.

ansver
Answers: 1

Another question on Business

question
Business, 05.02.2019 00:30
Can you name the traditional features of the mapuche economy? what are they?
Answers: 3
question
Business, 02.02.2019 06:33
Blank are decision makers who solve their problems using their instincts
Answers: 2
question
Business, 29.01.2019 20:21
What is the significance of the fact that the tv network nbc used to support its own world class symphony orchestra?
Answers: 3
question
Business, 29.01.2019 17:58
When recovery is first started, at what phase is the refrigerant removed to save recovery time?
Answers: 1
You know the right answer?
Given below is an excerpt from a management performance report:
budget actual difference
Questions
question
Mathematics, 28.01.2018 11:20
Questions on the website: 6551835